INFRASTRUCTURE FACILITY WORKS AT NEW INTERIOR ROP CAMPS – QARN ALAM

The scope infrastructure work at new interior ROP camps in Qarn Alam & Services those executed by AAS under this contract in Sultanate of Oman. The scope of work includes Engineering, Management, Procurement, Construction, Testing, Pre-commissioning and Commissioning. List of main activities under this contract and their control measures are described below:

 List of Activities to be Carried out during Infrastructure Work – ROP

  1. Mobilization / Demobilization
  2. Excavation
  3. Backfilling
  4. Thrust Boring
  5. HDPE pipe lying
  6. LV Lines
  7. Sewage Lifting Station
  8. Scaffolding Erection / WAH
  9. Rebar Work
  10. Shuttering/De shuttering work
  11. Block Work
  12. Concrete work
  13. Plaster Work
  14. Water Proofing
  15. Plant / Vehicle Movement
  16. Road Crossing – Graded Road & Black top
  17. Over Head Line (OHL) Crossing
  18. Pressure Test
  19. Live Pipelines Crossing